We prepared and implemented the commissioning of the 4 MW power-pack and drive for the world's largest heavy lift and pipe laying vessel. This involved the following work.

  • Writing a commissioning procedure
  • Pre-commissioning of the installation on site in Korea
  • Supervising the commissioning on site and during  the sea trials in Korea
  • We then supervised the changes and fine tuning during outfitting in the Netherlands.
  • In order to carry out a full load test we designed a special test manifold with a capacity of 6.400lpm @ 320 bar and then supervised the full load test.

In the meantime the Pioneering Spirit completed its first successful lift:

Commissioning 4MW central powerpack

  • img-2638.jpg
  • img-2639.jpg
  • pieter-schelte-40.png
  • img-0872.png
  • p6230030.png
  • img-1501.png
  • img-1505.png
  • dsc00669.png

                                    


SPECIALIST IN THE MARITIME SECTOR 

We speak the language of our customers and know how to get things moving quickly.


25 YEARS EXPERIENCe

We have more than twentyfive years of experience in complex projects. We are particularly strong in engineering and project management.


TURN-KEY SOLUTIONS

Together we can arrive at a smart solution that works and can be delivered within budget and on time.